Project Background
In order to ensure the project of the data center runs smoothly and goes live on time, the client chose our IT smart hands service and entrusted us with the unpacking, installation and cabling of 210 1U servers.
Project Challenges
Timeline: The client required the installation and configuration of all 210 servers to be completed within three days.
High technical requirements: Each server needed to be operated in strict accordance with the customer's specifications.
On-site coordination: The project is located in Finland, requiring real-time communication with the local team.
Project Solution
Pre-preparation: Communicate with the client in detail, clarify the specific requirements of each step, and set up a project team consisting of three senior engineers according to the requirements, each member of which has been working in the smart hand industry for many years.
Efficient execution: The three engineers worked eight hours a day and pushed the project forward in strict accordance with the plan. The team members cooperated with each other to ensure that each server was installed successfully.
Project Result
We successfully completed the unpacking, installation and cabling of 210 1U servers in three days, ensuring the smooth operation of the project.
Client Feedback
After the completion of the project, the client highly praised our services, especially the professional attitude and efficient execution of the engineer team.